Technical Review to our persistent sinkhole problems


The Engineering Department (Kejuruteraan) of MPSepang is having a technical review on the progress of IWK sewer line rectification work followed by YDP instruction to get it done  by this September. However the scope of rectification work is extended to cover a larger area for new sinkholes which including further variation order from IWK and MPSepang.

I was invited to the site briefing by the Pengarah kejuruteraan  Puan Nurulbaiti Binti Zainuldin and Assistant Engineer En Hairil of MPSepang together with IWK Engineer. Once a new work order is issued, the balance works is expected to be completed in next couple of months.

IMG_1956

Engineers from IWK, MPSepang and RA Chairman are inspecting the sinkhole near our guard house

IMG_1957

Further discussion about the sinkhole rectification work at our guard house

2 responses to “Technical Review to our persistent sinkhole problems

  1. We are glad that our Chairman taking time out to look into this problem and following up the matter with MP Sepang whenever he can. Good job!

  2. It’s really great that authority has shown their concern to the public. Indeed we are suffering alot from the sink hole issue. As a road user, our safety always put in the stake. Everyday and night we pass by the road, we always figure out that when will be the traffic cone at sink hole can be removed.

    Understand that this is the deep shit dedicated by the developer. I know, you know, the resident know and everyone will remember the best gift ever given by developer. Glad that IWK and authority have put the public interest in priority, scrutinize the root cause and rectify for the public.

    We hope the sink hole issue can be resolved soonest possible in order to return the safety to road user.